Hydrogeological services

Services · hydrogeology

Full-cycle hydrogeological services

Volkovgeology JSC carries out hydrogeological work to supply water to industrial facilities, shift camps and settlements: from calculating water demand and drilling wells to approving groundwater reserves and obtaining a special water use permit.

  1. Pre-design and financial planning

    Stage objective. Define the overall concept of the facility, calculate water demand and set the budget.

    • Collection and analysis of archive data: maps, earlier reports and data from neighbouring wells
    • Outline design of the facility
    • Water consumption and discharge balance: daily volumes for industrial, domestic and drinking needs and irrigation
    • Cost estimate covering design, drilling, equipment, laboratory analyses and state reviews
    • Approval of the facility’s location by the basin inspectorate, including water protection zones and strips
  2. Design, survey and field work

    Stage objective. Prepare the survey design, drill the well and measure its characteristics.

    • Hydrogeological work design, with a state or independent review for large facilities
    • Drilling a hydrogeological well to the aquifer
    • Pumping tests to determine the actual yield and drawdown
    • Well passport: depth, design, casing diameter, static and dynamic water levels
  3. Laboratory testing and review

    Stage objective. Confirm water safety and legalise the volumes of the groundwater source.

    • Chemical, bacteriological and radiological analysis of samples in an accredited laboratory
    • Sanitary and epidemiological opinion on compliance with sanitary standards
    • Hydrogeological study report and water intake model
    • Approval of reserves by the State or a Regional Reserves Committee where abstraction exceeds 1,000 m³ per day
  4. Permitting

    Stage objective. Obtain the legal right to abstract and use water.

    • Compiling the document package: calculations, well passport, sanitary opinion and land title documents
    • Application for a special water use permit via the eLicense.kz portal
    • Review by the basin inspectorate within 10 working days
    • Result: a special water use permit for up to 27 years with approved reserves

Projects

Hydrogeological work completed or under way under contracts with customers.

  • 2024–2025

    Customer

    Qazaq Stroy Industrial Projects LLP

    Prospecting and appraisal of groundwater for the industrial water supply of Taiqonyr Qyshqyl Zauyty LLP, Sozak District

  • 2025

    Customer

    Kazatomprom-SaUran LLP

    Exploration and appraisal of operational groundwater reserves in the Inkuduk and Mynkuduk aquifers for domestic, drinking and industrial water supply of work sites within the mining allotment of the Inkai deposit (section 3)

  • 2025

    Customer

    Eco Atameken public association

    Prospecting and appraisal of groundwater for the drinking water supply of Karatau, Karakur, Baba-Ata and Kyzylkanat, Sozak District, Turkistan Region

Company facilities

Water supply for the East Zhalpak shift camp

Two hydrogeological wells, pumping tests and a special water use permit. An autonomous source of industrial water reduces logistics costs and provides sanitary and living conditions for personnel at a remote site.

Planned

Social projectsDrinking water wells for villages in Sozak District and greening of the Aigene shift camp are described in the Sustainable Development section.